Single-phase vs. Three-phase Supply

Generally, you should change to a 3-phase supply if you have three (3) or more air-conditioners in your home. Upgrading to a 3-phase supply will increase stability and reliability of electricity supply to your premises.

A single-phase meter measures usage from a 230 volt supply through two (2) wires, while a 3-phase meter measures usage from a 415 volt supply through four (4) wires.

 
Fill Up Termination Form
  • Customer fills the electricity application form
a) Click here to Download Residential (Domestic) Application Form.
b) Click here to Download Commercial & Industrial (Non-Domestic) Application Form.
  • Attach together the required documents.
a) Example:
- Photocopy of NRIC
- Registered Sales & Purchase Agreement / Land Title / Tenancy Agreement / Offer Letter Memorandum of Transfer (wherever applicable)
- Consent Letter from Partner (if any)
- Business Registration Document (if registered under a company name)
- Company stamp (if registered under a company name)
  • Applicants must complete all the personal details and information before submitting the application form together with supporting documents as required by SESB.
 
Appoint Registered SESB Contractor
  • Appoint Electrical Wiring Contractor.Click here
  • The appointed Electrical Wiring Contractor shall fill up Form G and H.
  • The appointed Electrical Wiring Contractor shall submit the electricity application form together with the required documents to SESB
 
Pay Connection Charges
  • SESB will calculate the connection charges for the electricity connection to the premis.
  • Customer pays the connection charges and RM10 stamp duty.
 
Pay Deposit
  • Customer pays the electricity deposit
  • SESB installs meter and connects supply